08:30
|
REGISTRATION
AND REFRESHMENTS
|
09:00
|
MORNING
CHAIR’S OPENING REMARKS
Paul
Smith, Consultant, Nuclear New Build, Amec Foster Wheeler
|
|
SESSION ONE – MEETING THE
REGULATIONS, CODES AND STANDARDS
|
09.10
|
UPDATE ON HSE AGEING PLANT INITIATIVE
Ian Chapman, HM Specialist Inspector
Mechanical Engineering, HSE
|
09.40
|
WHAT HAPPENS TO PRESSURE VESSEL CODES
AND STANDARDS POST BREXIT?
David Nash, Vice Dean (Knowledge
Exchange) and Deputy Head of Department, Faculty of Engineering, University
of Strathclyde
- Overview of the current status of European pressure vessels codes
- The future of PD5500 - review of recent BSi survey on PD5500
- Engaging with the European pressure systems sector
|
10:00
|
WHAT PIPEWORK TO INSPECT TO MEET
LEGISLATIVE AND BUSINESS REQUIREMENTS AND HOW TO PRIORITISE
David Burgess, Principal Inspection
Consultant, ABB Consulting
- Overview of pipework inventory and systems assessment
- Criticality, priority and legislative requirements
- Assessment methodology and how to put this into practice
|
10:30
|
Networking
refreshment break
|
|
SESSION TWO – THE LATEST INDUSTRY
GUIDANCE
|
11:00
|
EEMUA 159 EDITION 4 – MANAGEMENT OF
AGEING STORAGE TANKS
Stuart Turner, Lead Oil and Gas
engineer, Scottish and Southern Energy
- Gain understanding of the basic requirements of ageing tank
management
- Main differences between EEMUA 159 Edition 3 and Edition 4
- Overview of future developments and new technologies
|
11:30
|
NON METALLIC EQUIPMENT – NEW SAFED
GUIDANCE IN RESPONSE TO PM75/86
Alan Hague, Technical Specialist
Pressure Systems, British Engineering Services Limited
- PM75 and PM86 overview
- PUWER and COMAH as applied to PM75 and PM86
- How SAFed IMG2 series can assist with inspecting to a Scheme of
Examination
|
12:00
|
MORNING
QUESTION AND ANSWER SESSION
|
12:25
|
NETWORKING
LUNCH
|
|
AFTERNOON
CHAIR
Peter
Batty, Chief Engineer, LmP Technical Services
|
|
SESSION THREE – INSPECTION AND
ASSESSMENT OF DEFECTS
|
13:25
|
NON-DESTRUCTIVE TESTING APPLICATION
FOR LATE LIFE CARE
Gordon Kanyike, Mechanical
Engineering Consultant, Amec Foster Wheeler
|
13:55
|
ENGINEERING CRITICAL ASSESSMENTS
(ECA)
John Sharples, Operations Manager
(Technical) and Chief Technologist (Structural Integrity), Materials Science
and Structural Integrity, Consulting, Amec Foster Wheeler
- General requirements for ECA and relevant codes and standards
- Understand ECA for crack-like defects
- Discover ECA for corrosion wall-thinning
|
14:25
|
NETWORKING
REFRESHMENT BREAK
|
|
SESSION FOUR – REPAIR
|
15:00
|
SPECIFYING, DESIGNING AND MANAGING
NON-WELDED REPAIRS FOR “LATE LIFE” PRESSURE EQUIPMENT
Adam Thistlewaite, Global Service
Line Director – On-Stream Repair, Team Furmanite
- Understand the key requirements in specifying repair scope
- Hear the benefits and limitations of non-welded metallic and
composite repair methods
- “Life of Asset” repairs: inspection and monitoring of repairs to
justify continued service
|
15:30
|
QUESTION
AND ANSWER SESSION
|
15:45
|
CHAIR’S
CLOSING REMARKS
|
16:00
|
END
OF SEMINAR
|